Data Center Pipeline Tracker

Announced → under construction → operational · the demand engine behind AI memory (Micron / HBM / DRAM)

Snapshot as of July 1, 2026 · sources: JLL, CBRE, Goldman Sachs, Sightline Climate, IEA, company filings · ask to refresh and this view updates

Of every 100% of announced AI data-center capacity, only about ~30% is actually under construction and roughly 50–60% ever comes online on schedule. The binding constraint is power, not compute or memory. That gap is the single best real-world governor on whether memory pricing holds or normalizes.

The announced → real funnel · US cohort with 2026 opening dates (Sightline Climate, ~140 projects)

Announced · 16 GW · 100%
Building · 5 GW
~31% actually under construction — poured concrete, not a press release
Not started · 11 GW
~69% announced with no sign of construction, despite 12–18 mo typical build time
On-time · ~50–60%
Goldman: only ~50–60% of near-term planned capacity lands on schedule · 30–50% delayed or cancelled
Announced Under construction Not started Expected on-time

Global installed base → 2030 (JLL / CBRE)

103 GWOperational now (Q1'26)
~200 GWProjected 2030
14% CAGR2026–2030
New capacity added 2026–2030~100 GW
Under-construction already pre-leased77% demand real
Vacancy (16 largest markets)6.7% tight ↓ from 8.3%
Read: what is actually being built is spoken-for. The vapor sits in the announcement layer, not the construction layer.

Hyperscaler capex 2026 · the money behind demand

Amazon
$200B
Google
$175–185B
Meta
$125–145B
Microsoft
$110–120B
Big-4 combined 2026~$725B +77% YoY
Incl. Oracle & others$700–900B
Spending is committed; the question is how fast it converts to energized capacity.

The bottleneck · power, not chips (IEA / grid data)

US interconnection queue stuck~2,300 GW > entire US grid
Avg wait in queue → operational~5 years
Grid capacity for a new DC24–36 months
High-power transformer lead time~5 yrs was 24–30 mo
Global DC electricity by 2030 (IEA)945 TWh
2026-scheduled projects hit by power delays~50%
The shell takes 12–18 months; the power takes years. A project can sit "announced" indefinitely waiting on a grid connection and a transformer — that is why ~70% of the announced cohort is untouched.

Read-through to Micron / memory

Watch-list · leading indicators to track over time

~30%
Announced → building conversion
77%
Under-construction pre-lease
6.7%
Market vacancy
~5 yr
Grid interconnect wait
A rising conversion rate + falling transformer lead times = supply catching demand = pressure on memory ASPs. A stalling conversion rate = shortage persists = pricing holds. This is the dial that decides the memory thesis.
Sources: JLL 2026 Global DC Outlook CBRE Q1'26 Goldman Sachs Sightline Climate (via Tom's Hardware) IEA Electricity 2030 Company capex filings